San Felipe Phase 2


The San Felipe EDM SF2 project is a 95MW expansion to the phase 1 project. Overall, we expect total a 135MW master plan project. Capacity has been reserved for the complete project and Enera expects all project entitlements to be complete by the Spring of 2020.

Status: Enera San Felipe Phase 2 (EDM SF1, S.R.L.)
Project Size: 95MW (total)
Location: San Felipe, Mexico
Estimated Annual Power Production: 1,850 MWh/MW/yr
Estimated Annual CO2 Offset: 322,200,000 lbs per year





Animation of 135MW master plan


  • SEMERNAT - Forestry, Complete
  • INASH, Complete
  • PPAs, Contracting Underway
  • Land Control / Land Status, Complete
    • Owned by Enera, Complete
    • Private Lands, Complete
  • MIA:
    • Application submitted
    • Expect March, 2020 completion
  • Social Impact Study:
    • Submitted
    • Expected Jan'2020
  • Interconnection
    • Indicative Study ~ 120MWac reserved, Complete
    • Impact Study, Underway, Expected complete March, 2020

sf1-layout